City begins street rehabilitation this week



The city this week begins the 2015/2016 Street Rehabilitation and Maintenance Project:

The preconstruction meeting was held on July 11, with the Notice to Pro­ceed confirmed for July 18. The con­tract calls for 70 days for construction.

The vacant city lot located at the corner of Bear Valley Parkway /Valley Parkway will be used as the staging yard. This site was chosen due to its central location to many of the streets being treated on this year’s project.